ACWA limits output at two Saudi solar plants

ACWA limits output at two Saudi solar plants

Acwa announces that two of its solar IPP plants have been subject to temporary limitation on power dispatch following instructions from the grid operator citing alleged reactive power fluctuations affecting grid stability, matters that both project companies deny.

Al Kahfah Solar PV IPP (1,425 MW) received the commercial operation certificate in November 2025 and thereafter has been under dispatch limitation since 12 December 2025, with partial dispatch permitted since 11 February 2026. The accumulated estimated revenue challenged by Principal Buyer up to March-end is approximately 95 million Saudi Riyals.

ArRass2 Solar PV IPP (2,000 MW) received the initial commercial operation certificate in September 2025 and thereafter has been under dispatch limitation since 16 January 2026, with partial dispatch permitted since 8 March 2026. The accumulated estimated revenue challenged by the Principal Buyer up to March-end is approximately SAR 73 million Saudi Riyals.

Both project companies have challenged the matter and are currently conducting detailed technical assessments, including independent third-party analysis, and coordinating with the relevant authorities to enable full restoration of plants operations.

Both companies have reserved all of their rights under the relevant project agreements and have issued deemed energy invoices in accordance with the terms of those agreements.Read More

No Comments

Sorry, the comment form is closed at this time.

Energy, Automobile, EV, Renewable News
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.