bp selects two consortiums to participate in FEED ‎competition for the Net Zero Teesside Power project

On behalf of its partners, bp – the operator of Net Zero Teesside Power (NZT Power) and ‎the Northern Endurance Partnership (NEP) – has awarded contracts as part of its dual Front ‎End Engineering Design (FEED) competition to two separate consortiums of engineering, ‎carbon capture licensors, power providers and EPC contractors.‎


The awards represent an important next step towards the proposed development of the UK’s ‎first full-scale integrated power and carbon capture project. Investing in carbon capture, usage ‎and storage (CCUS) is a key point of the UK government’s 10-point plan for a green industrial ‎revolution, announced in November 2020.


In October 2021, the UK government selected the Northern Endurance Partnership’s East ‎Coast Cluster as one of the first two clusters be taken forward as part of its carbon capture ‎and storage (CCUS) cluster sequencing process. The Northern Endurance partnership, which ‎bp leads as operator, will provide the common infrastructure needed to transport CO2 from ‎emitters across the Humber and Teesside to secure offshore storage in the Endurance aquifer ‎in the Southern North Sea.‎


The two groups will now design and submit development plans for NZT Power’s proposed ‎power station and carbon capture plant, and NEP’s planned Teesside high pressure carbon ‎dioxide (CO2) compression and export facilities.‎


The two selected contractor groups are:

  • Technip Energies and General Electric consortium: led by Technip Energies and ‎including Shell as a subcontractor for the provision of the licensed Cansolv CO2 capture ‎technology and Balfour Beatty as the nominated construction partner.‎
  • Aker Solutions Doosan Babcock and Siemens Energy consortium: led by Aker Solutions ‎and including Aker Carbon Capture as a subcontractor for the provision of the licensed ‎CO2 capture technology.‎

The two consortiums will each deliver a comprehensive FEED package, led from their UK ‎offices, over the next 12 months. Following the completion of the FEED process, the two ‎consortiums will then submit Engineering, Procurement and Construction (EPC) proposals for ‎the execution phase. As part of the Final Investment Decision expected in 2023, a single ‎consortium will be selected to take the project forward into construction.


Information Source: Read the article

Oil and gas, press , | Energy, Climate, Renewable, Wind, Biomass, Sustainability, Oil Price, LPG, Solar,Electric

#FOLLOW US ON INSTAGRAM
Energy, Automobile, EV, Renewable News
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.