Customize Consent Preferences

We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.

The cookies that are categorized as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ... 

Always Active

Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.

No cookies to display.

Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

No cookies to display.

Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customized advertisements based on the pages you visited previously and to analyze the effectiveness of the ad campaigns.

No cookies to display.

BorWin6 Project Begins

London, 05 July, 2023, (Oilandgaspress) McDermott held a first steel-cutting ceremony at its Jebel Ali fabrication yard in Dubai, United Arab Emirates, to mark the commencement of construction for the BorWin6 980MW high-voltage, direct current (HVDC) project for TenneT.

“We have successfully delivered engineering from our HVDC center of excellence in The Hague, and are on track to begin construction for this important offshore grid connection project,” said Vaseem Khan, McDermott’s Senior Vice President for Onshore. “During this next phase we will leverage our strategically located fabrication yards to drive execution excellence while maintaining our industry-leading safety record.”

Through a consortium with Global Energy Interconnection Research Institute Co., Ltd. and C-EPRI Electric Power Engineering Co., Ltd. (GEIRI / CEPRI), McDermott is providing engineering, procurement, construction, installation, and commissioning (EPCIC) services for an HVDC offshore converter platform, located offshore Germany. Electricity generated from offshore wind farms will be converted into direct current and transported to an onshore converter station located 146 miles (235 kilometers) onshore near Büttel, Germany. Here, the electricity is converted back into three-phase current and fed into the extra-high voltage grid.

Fabrication will be executed from McDermott’s fabrication yards in Dubai and Batam, Indonesia, which are both unrivalled in their ability to deliver complex offshore structures.

Building on the experiences of the BorWin6 project, McDermott was recently awarded an EPCIC contract by TenneT for two 2GW HVDC grid connection systems offshore Germany. It is the largest renewable project in McDermott’s growing energy transition portfolio and signifies its ongoing expansion into the thriving offshore wind market.