Customize Consent Preferences

We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.

The cookies that are categorized as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ... 

Always Active

Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.

No cookies to display.

Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

No cookies to display.

Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customized advertisements based on the pages you visited previously and to analyze the effectiveness of the ad campaigns.

No cookies to display.

Tata Power commissions India’s largest floating solar power project

Tata Power Solar Systems Limited (Tata Power Solar), a wholly-owned subsidiary of Tata Power, has accomplished a remarkable feat by commissioning India’s largest floating solar power project in Kayamkulam, Kerala on a 350-acre water body, backwaters area, having an installed capacity of 101.6 Megawatt Peak. This installation was completed within the stipulated period, despite the arduous challenges of variable water depths, high sea tides, and severe water salinity concerns faced throughout the project’s construction duration.

Tata Power Solar successfully built a scaffolding platform on the water body to make the entire solar plant float on water. This project is the first one in the Floating Solar Photovoltaic (FSPV) through Power Purchase Agreement category. This plant boasts a floating inverter platform having a 5 Megawatt (MW) capacity. The large-scale installation and commissioning of this 101.6 MWp capacity solar plant have been the fastest in the FSPV category, with ready a Commercial Operation Date (CoD) certification, which means the project has been nodded as complete and operational. The entire project is anchored to the waterbed of Kerala backwater using 134 cast pile foundations that are bored to a depth of 20 meters underwater to support the Central Monitoring and Control Stations (CMCS) and the 33/220 kilovolts switchyard. All this was done by dredging soil strata underwater, wherein the high groundwater was also a deterrent.

The entire array involving floats and solar panel modules had to be towed for 3 kilometers on a sea-linked National waterway, which was 15 meters deep, exposing the solar modules to high winds and gushing tides often reaching a height of about 3.5 meters. To operationalize the project, Tata Power Solar ‘s execution team was successfully able to synchronize the 33/220 Kilovolts Air Insulated Substation (AIS) with 220 Kilovolts existing Gas Insulated Substation (GIS).

Speaking about this remarkable feat, Dr. Praveer Sinha, CEO, and MD, Tata Power, said, “The commissioning of India’s first and largest floating solar project is an innovative and incremental step toward meeting India’s sustainable energy goals. We are incredibly proud of our team’s unrelenting efforts in delivering this unique solar project that floats atop a large waterbody.”

A power purchase agreement has been signed with a PSU client, wherein the entire power generated from this plant will be used by Kerela State Electricity Board (KSEB). Interestingly, all the solar modules used in this plant were safely transported, unloaded, and stored on a limited parcel of land for about 35 days by Tata Power Solar. In its construction stages, the plant also adequately housed a team of 350 personnel who were tasked with speeding up the project as per contract agreements.