Customize Consent Preferences

We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.

The cookies that are categorized as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ... 

Always Active

Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.

No cookies to display.

Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

No cookies to display.

Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customized advertisements based on the pages you visited previously and to analyze the effectiveness of the ad campaigns.

No cookies to display.

UK’s National Grid fast-tracks overhead line upgrade project

London, 18 December 2023, (Oilandgaspress): – National Grid has accelerated engineering works to address a bottleneck in connecting low carbon projects to the electricity network in South West England and Wales.

The 82km upgrade of one its high voltage overhead electricity lines, between Bramley in Hampshire and Melksham in Wiltshire, has been brought forward to help accelerate the connection of 175 clean energy projects to the grid.

The £90 million investment includes replacing conductors – the wires strung between the 229 transmission towers (known as pylons) on the route – with new cables which can operate at a higher temperature and therefore allow more power to pass through the transmission circuit.

The upgrade of approximately 3000MVA (Megavolt-Amperes) will allow increased flow of electricity out of South West England on the high voltage network, removing a constraint for the 175 projects looking to connect in the region which currently have connection dates of 2028 and beyond.

The project has been brought forward a year and will now begin in January 2024, finishing in October 2025, with National Grid – in partnership with the ESO – discussing accelerated connection dates with customers as part of each individual project’s development.

This upgrade follows National Grid’s recent announcement of accelerating up to 20GW of grid connections across its transmission and distribution networks (the equivalent capacity of six Hinkley Point C nuclear power stations), including accelerating 10GW of battery storage projects by up to four years.

National Grid is also working closely with both the ESO and Energy Networks Association (ENA) on their plans to reform the connections process, both of which are key parts of the government’s recently published Connection Actions Plan.


Information Source: Read full article